Management Experience Related Question
What are the authoritative approval and procedure for a road enhancing work?
Introduction
Enhancement of road will be requested by authority such as
JKR state and district when a project is at main road side of either federal or
state road. It is a pre-requisite prior to planning approval especially the
project occupies big area. The big development, once completed, will result
high volume of traffic into and from the developed area into main road. Hence,
it is reasonable that road enhancement being requested by authority to
streamline the traffic at main road.
The following are items and stages of approval of proposed
road enhancement work, which are needed to be presented and submitted to “Unit
Pengurusan Projek Cawangan Jalan”, “Unit Keselamatan Jalan (Cawangan Jalan)”.
Both the units are from JKR.
1) Traffic
Impact Assessment – traffic volume in coming future.
It is evaluation of current road
and traffic situation plus projection (prediction) of future traffic condition
of probably 10 years later.
The report shall be prepared by
third party engineer, will cover current utilization of the road type (like
federal road R5) and estimation (prediction) of the possible utilization in
future due to grow of traffic and upon completion of new project.
The findings, as earlier paragraph,
will be presented and recommendation will be included such as road enhancement
and installation of traffic light system.
2) Road
safety audit-1 : Conceptual design dwgs.
This stage could have been started
before TIA and shall be reviewed by road design engineer upon completion of TIA
by another party. The conceptual design dwgs will have to be submitted to
another appointed Road Safety Auditor.
The RSA auditor will be prepared a
report with recommendation.
3) Road
safety audit-2 : Preliminary design drws.
This is next stage of RSA-1,
preliminary design drws will have to be submitted to RSA auditor for his review
and recommendation.
4) Road safety audit-3 : Detailed design drws.
With permission from JKR, road
design engineer could proceed directly to detailed design drws, without both
RSA-1 and RSA-2. The detailed design shall cover proposed final road alignment,
road furniture, traffic light system, relocation of utility, etc.
The detailed design shall take into
consideration of all recommendation of TIA. Then, the design is submitted for
RSA auditor for review and recommendation.
5) Road
safety audit-4 (Stage 1, 2 & 3) : Construction and Traffic Management
Drws (Stage 1), Corrective Action (Stage 2 & 3) prior to work approval.
There are 3 sub-stage for RSA-4.
The first sub-stage is construction
and traffic management plan. This is planning of traffic management during
construction work. A traffic management officer (TMO) will have to be
appointed. The TMO will have to monitor and supervise the approved traffic
management plan implemented effectively. Work approval will only granted by JKR
if the traffic management plan and RSA-4 satisfy them.
The second and third of RSA-4 are
corrective actions to traffic management plan and road construction works during
ongoing construction. Supervision team members such the project Superintending
Officer (S.O.) and engineer will have to ensure contractor to implement
corrective actions prior to proceeding of works.
6) Road
safety audit-5: Audit after issuance of CPC (approx. 3~6 months).
This is the last stage of the RSA
process, which is to be carried out probably after 3 to 6 month after project
completion and open to traffic. The RSA auditor, at this time, to check and
review the efficiency of the design. Or else, recommendation and remedy work
will be recommended.
Conclusion
For project, which is located next to main road (federal
road) or when a new junction to main road is proposed, an independent Traffic
Impact Officer will have to be appointed to conduct the study on the existing
road and traffic and also the impact upon completion of project and new
junction.
In addition, a road safety auditor who is independent too,
will have needed to audit the road designer’s design, ongoing construction
condition and as-built condition.
No comments:
Post a Comment